- Home
- Government
- Public Works
- Divisions
- Engineering
- Projects
- 19-18: 2020 Street Reconstructions - Area 2
Create an Account - Increase your productivity, customize your experience, and engage in information you care about.
During the week of August 17 the contractor will be:
The project will fully reconstruct the above streets with new pavement and concrete curb and gutter and additional storm sewer catch basins at select locations. Watermain work will be generally limited to hydrant replacements and no sanitary sewer work is anticipated. The streets will remain the same width and configuration as they currently are. The general construction process is as follows:
It is the goal of the project to keep access available at all times for those residents that take direct access off of the project streets but the road surface will be gravel during most of the project. There may be short term delays for access to or from your driveway or on the road where you may have to wait for the construction equipment to pass by. During curb and gutter installation and driveway apron replacement, there will be a period of days where residents will not be able to access their driveways and all parking must be done on street. Residents will receive notification prior to any driveway closures. The project is anticipated to take approximately four months to complete.