105th Avenue Reconstruction Update 05/02/2018

Posted on May 2, 2018 at 8:27 AM by Heidi Andrea

This week the contractor is back to work on 105th Avenue,  they are working on completing the installation of the storm sewer and water main on the middle portion of the project, between Davenport Street and Nassau Street.  Their second crew is grading the pond located at Davenport and using the material to finish grade the site.  They are also installing the aggregate base starting on the east end in preparation for the curb installation, coming soon.   The signal crew is also on site preparing the new signal system at Davenport Street; several of the new signal bases will be installed this week.

Next week the utility crew will be focusing on the west end of the project and are expected to complete the installation of the storm sewer and water main.

Please Note:
Traffic at the intersection for 105th Avenue and Davenport will now see minor delays as the contractor’s construction activities will be in and around the intersection.  Drivers will need to be patient and should avoid the area if possible.  

Tag(s): 105th Avenue