105th Avenue Reconstruction Update 06/21/2018

Posted on June 21, 2018 at 1:03 PM by Heidi Andrea

This week the contractor continues to finish grade the boulevards on the north side of the project.  The irrigation crew is now on site laying out and installing the irrigation along the northern boulevard.  The temporary signal at Davenport will be removed, and the permanent signal will be turned on.

Next week the contractor will start to finish the concrete work in the medians and begin finish grading.  Irrigation and landscape crews will be working in both roundabouts.
 
Traffic should use caution as traffic will now be split for the third phase of the project.  One westbound lane on the north side and one eastbound lane on the south side.