22-05: 89th Avenue and Davenport Area Street Reconstructions
Location
- Baltimore Street from 85th Avenue to 89th Avenue
- Davenport Street from 85th Avenue to 89th Avenue
- 89th Avenue from Central Avenue (MN-65) to Davenport Street
- 87th Avenue from Central Avenue (MN-65) to Hastings Street
- Eldorado Street from 85th Avenue to 87th Avenue
- Goodhue Street from 85th Avenue to 87th Avenue
- Goodhue Street from 87th Avenue to northerly dead end
- Jenkins Court from 85th Avenue to the cul de sac
Project Status as of 5/11/2023
The project consists of five phases which can be seen on the project phasing map. Phase 1 was completed in 2022, with phases 2-5 being constructed in 2023.
Phase 1
Construction completed in 2022.
Phase 2
Construction activities during the week of May 15 will include:
- Street grading
- Installation of concrete curb and gutter
Phase 3
Construction is anticipated to begin the week of May 15 and will include:
- Milling the upper 1.5 inch of existing bituminous surface
- Spot concrete curb and gutter replacement
Phases 4-5
Construction is anticipated to begin the week of June 19 (subject to change).
If you have any questions regarding the project, please contact Bolton & Menk inspector Travis Pearl at 612-599-3191 or travis.pearl@bolton-menk.com.
For more information, visit BlaineMN.gov/22-05.