BlaineMN.gov - Construction Update

Welcome to the Blaine Construction Update

The construction update is published during the construction season and includes details about current road construction projects happening in the City of Blaine. You can subscribe to email notifications by visiting the notify me page and selecting Blaine Construction Update.


21-30: Lift Station 13 Force Main Replacement Project - Phase 1


Location

West 35W Service Drive from 93rd Avenue to 95th Avenue.  Green space area between 95th Avenue and Naples Street.

Project Status as of 10/9/2023

The project location can be seen on the 21-30 Location Map.

West 35W Frontage Road is currently closed from 93rd Avenue to 95th Avenue. This road closure is anticipated to last until November 20. Construction activities during the week of October 9 will include:

  • Installation of trenchless sanitary sewer crossing at 95th Avenue
  • Installation of new sanitary sewer main

For additional project information, visit BlaineMN.gov/21-30.


23-06: Northwest Area Street Reconstruction

Location

Project Area 1

  • 127th Avenue from cul-de-sac to Polk Street
  • 127th Lane from Monroe Street to Polk Street
  • 128th Avenue from Taylor Street to Polk Street
  • 129th Lane from 175 feet west of Tyler Street to Polk Street
  • Tyler Street from 127th Lane to 129th Lane
  • Polk Street from 126th Avenue to cul-de-sac

Project Area 2

  • 131st Avenue (E) from Van Buren Street to Taylor Street

Project Area 3

  • 131st Avenue (W) from Jefferson Street to Van Buren Street

Project Status as of 10/9/2023

The project consists of two phases, which can be seen on the project phasing map.

Phase 1

Construction activities during the week of October 9 will include:

  • Irrigation system repairs
  • Boulevard grading and restoration

Phase 2

Construction activities during the week of October 9 will include:

  • Irrigation system repairs
  • Boulevard grading and restoration

If you have any questions regarding the project, please contact SEH inspector Erik Navratil at 612-257-4184 or enavratil@sehinc.com.

For more information, visit BlaineMN.gov/23-06.


23-08: Southeast Area Street Reconstruction

Location

Project Area 1

  • 97th Lane from Austin Street to Lexington Avenue
  • 98th Avenue from Austin Street to Cord Street
  • 98th Lane from Austin Street to Cord Street
  • 99th Avenue from Austin Street to Lexington Avenue
  • Austin Street from Edgewood Road to 97th Lane
  • Austin Street from 98th Avenue to Lexington Avenue
  • Cord Street from 98th Avenue to Austin Street
  • Edgewood Road cul-de-sac (4023-4083)
  • Edgewood Road cul-de-sac (4103-4163)

Project Area 2

  • West 35W Service Drive from West 35W Service Drive to cul-de-sac

Project Area 3

  • Edison Street from 85th Avenue to cul-de-sac

Project Area 4

  • 89th Lane from Yancy Street to 90th Lane
  • 89th Court from 90th Lane to cul-de-sac
  • 90th Lane from Zumbrota Street to Rice Creek Parkway
  • Bataan Street from 90th Lane to 91st Avenue
  • Yancy Street from Rice Creek Parkway to 89th Lane
  • Zumbrota Street from 89th Lane to 91st Avenue
  • Bataan Court from 89th Lane to cul-de-sac
  • Zumbrota Circle from Zumbrota Street to cul-de-sac

Project Status as of 10/9/2023

The project consists of four project areas, which can be seen on the project phasing map. Project newsletters were mailed out on Friday, May 19.

Project Area 1

Construction has been completed in project area 1 except for minor punch list items which will be completed this fall.

Project Area 2

Construction has been completed.

Project Area 3

Construction has been completed in project area 3 except for minor punch list items which will be completed this fall.

Project Area 4

Construction has been completed in project area 4 except for minor punch list items which will be completed this fall.

If you have any questions regarding the project, please contact WSB inspector Sam Gonsior at 651-380-3272 or sgonsior@wsbeng.com.

For more information, visit BlaineMN.gov/23-08.

Contact Us

This information has been shared with you by the City of Blaine engineering department.

Engineering Department
lgray@blainemn.gov
763-785-6172

Visit us on the web at BlaineMN.gov/Engineering.

Share on Facebook
Share on Twitter
Share via Email

Copyright 2023 City of Blaine. All Rights Reserved.
10801 Town Square Drive NE, Blaine MN 55449

Powered by
CivicSend - A product of CivicPlus